Anza urges Agave 4.4.1 before epoch 1079

On 5 November 2026 Anza told mainnet-beta validators to move to Agave 4.4.1. Nodes without the patch are planned to fork off at epoch 1079 on 6 November, at about 2:30 p.m. Berlin.

On 5 November 2026 Anza urged mainnet-beta validators to upgrade to Agave 4.4.1. Nodes without the patch are planned to fork off the network at epoch 1079. Anza sets that plan at about 13:30 UTC on 6 November, which is 2:30 p.m. Berlin.

The patch applies a minimum loaded data size to loader-v3 ProgramData accounts. GitHub release 4.4.1 is marked stable and recommended for general use, including testnet and devnet. It was published on 5 November.

Firedancer v26.10.6, published the same day, adds support for the feature loaderv3_programdata_size_floor. Anza’s post names Agave 4.4.1. It does not give a Firedancer cutoff.

Anza tells operators to upgrade and to watch the node.

What to watch

  • Whether epoch 1079 began on 6 November at about 2:30 p.m. Berlin.
  • Whether other validator clients share that cutoff.